/50

FAQ’s for Project Management Jobs

1 / 50

1. Which one describe the ability to work successfully for a project to meet the futuristic goals?

2 / 50

2. Project Repot includes what from the below mentioned options?

3 / 50

3. Which one is an indirect tax?

4 / 50

4. Rectifications of identified correcttions in cash-book are done using which colur pen?

5 / 50

5. In which form no the hand receipt are maintained?

6 / 50

6. What is the meaning of intermediate payment?

7 / 50

7. Which instrument is commonly used for sending an alerts message before starting of danger work?

8 / 50

8. From the security point of view what is the most suitable time of demolition?

9 / 50

9. What are the cause of the accidents in the project site?

10 / 50

10. From the given below options choose the functions of the inspection department?

11 / 50

11. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?

12 / 50

12. What is the process called in which the actual field or site progress is compared with the estimated progress?

13 / 50

13. What are the following tools are required for the analysis of progress?

14 / 50

14. The analysis of progress of a project is done to achieve?

15 / 50

15. By whome the Job layout is prepared?

16 / 50

16. The systematic placement of resources in site are termed as?

17 / 50

17. The materials stored at the site should be protected from?

18 / 50

18. Why do we use Job layout facilitate in construction work to proceed?

19 / 50

19. What is the aim of organising labour at the site?

20 / 50

20. Name the unit provided for fire hazards safety purposes?

21 / 50

21. What are the factors on which the job layout for any project will depend?

22 / 50

22. Who are involved in selection of a construction site?

23 / 50

23. Which type of organisation is very popular in Civil Engineering Constructions?

24 / 50

24. Which of the following is an event ?

25 / 50

25. Time and progress chart of a construction project is?

26 / 50

26. Which one of the following is not a resource of construction industry?

27 / 50

27. In construction project owner may be functional as?

28 / 50

28. What is the main function of the construction management?

29 / 50

29. From the below mentioned optiones which of the following is not arole of the owner

30 / 50

30. In PWD which type of organization is is widely used

31 / 50

31. Consider the following statements regarding slack, choose the correct option; a) The free slack never exceeds the total slack b) The jobs that have total slack need not necessarily have the free slack c) A job can have a free slack only if it has more total slack that the one of its immediate successors.

32 / 50

32. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.

33 / 50

33. A CPM family includes which of the following?

34 / 50

34. Critical Path network helps an engineer to understand?

35 / 50

35. In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is?

36 / 50

36. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be?

37 / 50

37. Which one of the following represents an event?

38 / 50

38. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as?

39 / 50

39. Which one of the following represents an activity?

40 / 50

40. The difference between the time available to do a job and the time required to do the job, is known as?

41 / 50

41. The performance of a specific task in CPM, is known as?

42 / 50

42. PERT analysis is based on?

43 / 50

43. For the supply of materials for concrete, farm work reinforcing and placing of concrete, removal of farm work and curing of concrete, number of bar(s) required on bar chart, is?

44 / 50

44. Various activities of a project, are shown on bar charts in which format?

45 / 50

45. An Executive Engineer may have powers to approve amount up to?

46 / 50

46. Military organization is known as which type of organization?

47 / 50

47. While filling the tender for any work, the contractor considers which of the following?

48 / 50

48. Modular co-ordination of construction means proper?

49 / 50

49. The final selection of a construction site, is done by?

50 / 50

50. What should be the minimum cost of a work to be called as project?

Your score is