FAQ’s for Project Management Jobs
1 / 50
1. Which one describe the ability to work successfully for a project to meet the futuristic goals?
2 / 50
2. Project Repot includes what from the below mentioned options?
3 / 50
3. What is the full form of PPP?
4 / 50
4. Rectifications of identified correcttions in cash-book are done using which colur pen?
5 / 50
5. Tools and plants purchased for general use of division shall be debited to Which Catogery?
6 / 50
6. To the contractor we make the payment for work done but the quantity is not measured at the time of payment is called as?
7 / 50
7. All measurements of a work or project are entered in?
8 / 50
8. The muster roll is maintained in which form no ?
9 / 50
9. The Triangle of construction management completes with?
10 / 50
10. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?
11 / 50
11. The data or the information obtained through the various methods of progress record such as measurement book, job diary, progress report etc, are quantified and analyzed. Name what do we call this process as?
12 / 50
12. What are the following tools are required for the analysis of progress?
13 / 50
13. The minimum number of labour required for the applicability of Contract Labour Act?
14 / 50
14. According to minimum wages act normal working hours for adult workers is?
15 / 50
15. The systematic placement of resources in site are termed as?
16 / 50
16. Why do we use Job layout facilitate in construction work to proceed?
17 / 50
17. What is the aim of organising labour at the site?
18 / 50
18. Name the unit provided for fire hazards safety purposes?
19 / 50
19. Which type of organisational structure is mostly followed in civil construction?
20 / 50
20. What are the factors on which the job layout for any project will depend?
21 / 50
21. What are the main advantage of line organisation?
22 / 50
22. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?
23 / 50
23. Contractor focuses on which one of the follwing during the tender filling process?
24 / 50
24. Finishing of any activity which falls in a CPM network is known as?
25 / 50
25. Construction of the power station comes in which type of construction as per the options mentioned below
26 / 50
26. What does the Construction team means?
27 / 50
27. As pet the below mentioned optioned each work should be planned with respect to?
28 / 50
28. What is the main function of the construction management?
29 / 50
29. What are the qualities of good construction manager?
30 / 50
30. At which stage the contract documents are prepared?
31 / 50
31. What is an organization?
32 / 50
32. A project has three independent critical paths A, B and C. To reduce the project length, which one we have to shorten?
33 / 50
33. Consider the following statements regarding slack, choose the correct option; a) The free slack never exceeds the total slack b) The jobs that have total slack need not necessarily have the free slack c) A job can have a free slack only if it has more total slack that the one of its immediate successors.
34 / 50
34. What is PERT?
35 / 50
35. In a project logic, four activities M, N, 0 and P are to be completed before starting activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr. respectively, the earliest event occurrence time for the activity Q is?
36 / 50
36. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to?
37 / 50
37. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?
38 / 50
38. The difference between the time available to do a job and the time required to do the job, is known as?
39 / 50
39. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as?
40 / 50
40. An event is indicated on the network by a number enclosed in which symbol?
41 / 50
41. The performance of a specific task in CPM, is known as?
42 / 50
42. Completion of an activity on CPM network diagram, is generally known as?
43 / 50
43. Various activities of a project, are shown on bar charts in which format?
44 / 50
44. Site order book is used for recording what?
45 / 50
45. The Overall in-charge of an organization at the site responsible for the execution of the works, is called as?
46 / 50
46. Henry Gantt developed Bar charts for planning and scheduling of projects in which year?
47 / 50
47. What is the main principle of an organization?
48 / 50
48. A construction schedule is prepared after collecting which of the following data?
49 / 50
49. What is the object of technical planning?
50 / 50
50. Power stations are generally treated as which type of construtions?
Your score is
Restart quiz