FAQ’s for Project Management Jobs
1 / 50
1. In which Report do we get the specific activities, events and occurrences?
2 / 50
2. What is the full form of DPR?
3 / 50
3. If any product is imported by any company from abroad, then which tax is applicable on it?
4 / 50
4. Which one is an indirect tax?
5 / 50
5. For issue of the stock at store a price per unit is fixed. What is the price called as?
6 / 50
6. For allotment of work quotations are invited in which type of system?
7 / 50
7. Which instrument is commonly used for sending an alerts message before starting of danger work?
8 / 50
8. Brand value of any construction firm is created because of?
9 / 50
9. The Triangle of construction management completes with?
10 / 50
10. Select the type of measurement book used by the junior engineer from the given options?
11 / 50
11. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?
12 / 50
12. The data or the information obtained through the various methods of progress record such as measurement book, job diary, progress report etc, are quantified and analyzed. Name what do we call this process as?
13 / 50
13. Which is the famous trade union of India ?
14 / 50
14. The minimum number of labour required for the applicability of Contract Labour Act?
15 / 50
15. The systematic placement of resources in site are termed as?
16 / 50
16. Why do we use Job layout facilitate in construction work to proceed?
17 / 50
17. Name the unit provided for fire hazards safety purposes?
18 / 50
18. The major principle of storing and stacking of any materials is to achieve with?
19 / 50
19. What are the factors on which the job layout for any project will depend?
20 / 50
20. What is the first stage of a construction?
21 / 50
21. Which of the following does not represent an activity?
22 / 50
22. An event is represented in the network through which symbol?
23 / 50
23. Which one of the following is not a resource of construction industry?
24 / 50
24. As per the term economic activity the second largest industry in India is?
25 / 50
25. A contractor in construction of a project is
26 / 50
26. At which stage the tests for performance of construction is done
27 / 50
27. Supervision for quality control is the part of which stage
28 / 50
28. From the below mentioned optiones which of the following is not arole of the owner
29 / 50
29. In PWD which type of organization is is widely used
30 / 50
30. What arethe 4M of construction?
31 / 50
31. Pick up the correct statement regarding PERT from the below mwntioned options?
32 / 50
32. Consider the following definitions regarding slacks of project activities, from the below mentions options a) The difference between the early start and late start times of a job is called the total slack. b) The critical path is the one whose jobs have zero total slack c) The amount of time by which a job can be delayed without affecting the early start time of any job is called as the free slack d) The difference between the total slack of an activity and the minimum total slack of all its immediate successors is called as free slack.
33 / 50
33. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.
34 / 50
34. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.
35 / 50
35. A CPM family includes which of the following?
36 / 50
36. An event is indicated on the network by a number enclosed in which symbol?
37 / 50
37. While scheduling a project by P.M what does he consider?
38 / 50
38. PERT analysis is based on?
39 / 50
39. An Executive Engineer may have powers to approve amount up to?
40 / 50
40. Final technical authority of a project lies with whome?
41 / 50
41. What is the main feature of functional organization?
42 / 50
42. What is the most popular type of organization used for Civil Engineering Constructions?
43 / 50
43. A construction schedule is prepared after collecting which of the following data?
44 / 50
44. What is the main advantage of line organization?
45 / 50
45. Military organization is known as which type of organization?
46 / 50
46. While filling the tender for any work, the contractor considers which of the following?
47 / 50
47. Modular co-ordination of construction means proper?
48 / 50
48. What is the object of technical planning?
49 / 50
49. Construction team includes the following resources?
50 / 50
50. Railway projects are treated as which type of construtions?
Your score is
Restart quiz