/50

FAQ’s for Project Management Jobs

1 / 50

1. Project Repot includes what from the below mentioned options?

2 / 50

2. In india which type of tax system is found?

3 / 50

3. What is the abrevation of TCO?

4 / 50

4. A bussiness started by an enterpreneus with a fresh idea is performing which type of role in busines?

5 / 50

5. Rectifications of identified correcttions in cash-book are done using which colur pen?

6 / 50

6. Public Works Department executes projects primarly of which department?

7 / 50

7. For issue of the stock at store a price per unit is fixed. What is the price called as?

8 / 50

8. Tools and plants purchased for general use of division shall be debited to Which Catogery?

9 / 50

9. In which form number the measurement Book is maintained?

10 / 50

10. To the contractor we make the payment for work done but the quantity is not measured at the time of payment is called as?

11 / 50

11. In which form no the hand receipt are maintained?

12 / 50

12. For allotment of work quotations are invited in which type of system?

13 / 50

13. For the success of any construction project what characteristics is/are required?

14 / 50

14. Select the type of measurement book used by the junior engineer from the given options?

15 / 50

15. The analysis of progress of a project is done to achieve?

16 / 50

16. The minimum number of labour required for the applicability of Contract Labour Act?

17 / 50

17. A site engineer should ensure to have best output of the work given to the labour must be?

18 / 50

18. The materials stored at the site should be protected from?

19 / 50

19. Why do we use Job layout facilitate in construction work to proceed?

20 / 50

20. What is the first stage of a construction?

21 / 50

21. Who are involved in selection of a construction site?

22 / 50

22. Line organisation is other wise known as?

23 / 50

23. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?

24 / 50

24. What is Slack time?

25 / 50

25. An event is represented in the network through which symbol?

26 / 50

26. Time and progress chart of a construction project is?

27 / 50

27. Finishing of any activity which falls in a CPM network is known as?

28 / 50

28. Which one of the following is an activity?

29 / 50

29. As per the term economic activity the second largest industry in India is?

30 / 50

30. As pet the below mentioned optioned each work should be planned with respect to?

31 / 50

31. In PWD which type of organization is is widely used

32 / 50

32. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.

33 / 50

33. from the below given options choose which is an PERT event?

34 / 50

34. The time which results in the least possible construction cost of an activity, is known as?

35 / 50

35. Critical path lies along the activities having total float?

36 / 50

36. In a project logic, four activities M, N, 0 and P are to be completed before starting activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr. respectively, the earliest event occurrence time for the activity Q is?

37 / 50

37. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be?

38 / 50

38. Which one of the following represents an event?

39 / 50

39. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as?

40 / 50

40. PERT analysis is based on?

41 / 50

41. Choose from the following what does a milestone chart represent as?

42 / 50

42. Various activities of a project, are shown on bar charts in which format?

43 / 50

43. Site order book is used for recording what?

44 / 50

44. An Executive Engineer may have powers to approve amount up to?

45 / 50

45. Final technical authority of a project lies with whome?

46 / 50

46. The main disadvantage of line organization is?

47 / 50

47. What is the main advantage of line organization?

48 / 50

48. The final selection of a construction site, is done by?

49 / 50

49. Power stations are generally treated as which type of construtions?

50 / 50

50. What should be the minimum cost of a work to be called as project?

Your score is