/50

FAQ’s for Project Management Jobs

1 / 50

1. In which Report do we get the specific activities, events and occurrences?

2 / 50

2. Which one is an indirect tax?

3 / 50

3. Rectifications of identified correcttions in cash-book are done using which colur pen?

4 / 50

4. In which form number the measurement Book is maintained?

5 / 50

5. Which of these works are included in Public Works Department?

6 / 50

6. Choose which one are required in a Tender?

7 / 50

7. From the security point of view what is the most suitable time of demolition?

8 / 50

8. to achieve good quality what do we require?

9 / 50

9. What are the cause of the accidents in the project site?

10 / 50

10. From the given below options choose the functions of the inspection department?

11 / 50

11. What are the following tools are required for the analysis of progress?

12 / 50

12. Name the unit provided for fire hazards safety purposes?

13 / 50

13. Which type of organisational structure is mostly followed in civil construction?

14 / 50

14. What are the factors on which the job layout for any project will depend?

15 / 50

15. The plan which shows the exact location for placing the resources for construction is known as?

16 / 50

16. Line organisation is other wise known as?

17 / 50

17. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?

18 / 50

18. Contractor focuses on which one of the follwing during the tender filling process?

19 / 50

19. What does the critical activity shows?

20 / 50

20. Finishing of any activity which falls in a CPM network is known as?

21 / 50

21. Which one of the following is not a resource of construction industry?

22 / 50

22. As per the term economic activity the second largest industry in India is?

23 / 50

23. Construction of the power station comes in which type of construction as per the options mentioned below

24 / 50

24. What are the qualities of good construction manager?

25 / 50

25. Road is included in which type of constructions mentioned below

26 / 50

26. A project has three independent critical paths A, B and C. To reduce the project length, which one we have to shorten?

27 / 50

27. Pick up the correct statement regarding CPM from the below mentioned options?

28 / 50

28. Consider the following statements regarding slack, choose the correct option; a) The free slack never exceeds the total slack b) The jobs that have total slack need not necessarily have the free slack c) A job can have a free slack only if it has more total slack that the one of its immediate successors.

29 / 50

29. Pick up the correct statement regarding PERT from the below mwntioned options?

30 / 50

30. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.

31 / 50

31. from the below given options choose which is an PERT event?

32 / 50

32. What is CPM?

33 / 50

33. Critical path lies along the activities having total float?

34 / 50

34. Critical Path network helps an engineer to understand?

35 / 50

35. Pick up the correct statement from the following?

36 / 50

36. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?

37 / 50

37. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be?

38 / 50

38. For completion of a project, the critical path of the network represents?

39 / 50

39. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to?

40 / 50

40. The estimated time required to perform an activity, is known as?

41 / 50

41. What is a dummy activity?

42 / 50

42. An event is indicated on the network by a number enclosed in which symbol?

43 / 50

43. While scheduling a project by P.M what does he consider?

44 / 50

44. Critical path method is?

45 / 50

45. Bar charts are suitable for which types of works?

46 / 50

46. Site order book is used for recording what?

47 / 50

47. What is the main principle of an organization?

48 / 50

48. What is the main feature of functional organization?

49 / 50

49. The main disadvantage of line organization is?

50 / 50

50. What is the main advantage of line organization?

Your score is