FAQ’s for Project Management Jobs

1 / 50

1. Project Repot includes what from the below mentioned options?

2 / 50

2. Which one is an indirect tax?

3 / 50

3. Public Works Department executes projects primarly of which department?

4 / 50

4. For allotment of work quotations are invited in which type of system?

5 / 50

5. Which one is these is an psychological cause of accident?

6 / 50

6. At which stage of construction, the inspection is required for error-free work to be executed?

7 / 50

7. What are the cause of the accidents in the project site?

8 / 50

8. What can we stop using Inspection for the site?

9 / 50

9. From the given below options choose the functions of the inspection department?

10 / 50

10. What do we call the charts used for the graphical representation of the operation analysis?

11 / 50

11. Select the type of measurement book used by the junior engineer from the given options?

12 / 50

12. What are the following tools are required for the analysis of progress?

13 / 50

13. According to minimum wages act normal working hours for adult workers is?

14 / 50

14. By whome the Job layout is prepared?

15 / 50

15. What is the aim of organising labour at the site?

16 / 50

16. What are the factors on which the job layout for any project will depend?

17 / 50

17. What is or are the main disadvantage of the line organisation is?

18 / 50

18. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?

19 / 50

19. What is Slack time?

20 / 50

20. Which of the following is an event ?

21 / 50

21. An event is represented in the network through which symbol?

22 / 50

22. Contractor focuses on which one of the follwing during the tender filling process?

23 / 50

23. Time and progress chart of a construction project is?

24 / 50

24. What is the main factor which affects the construction of project most?

25 / 50

25. Which of these is the first largest industry in India in term of economic activity?

26 / 50

26. What does the Construction team means?

27 / 50

27. What is the main function of the construction management?

28 / 50

28. Which of the following is not a characteristics of a Good organization ?

29 / 50

29. A project has three independent critical paths A, B and C. To reduce the project length, which one we have to shorten?

30 / 50

30. Consider the following statements regarding slack, choose the correct option; a) The free slack never exceeds the total slack b) The jobs that have total slack need not necessarily have the free slack c) A job can have a free slack only if it has more total slack that the one of its immediate successors.

31 / 50

31. Pick up the correct statement regarding PERT from the below mwntioned options?

32 / 50

32. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.

33 / 50

33. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.

34 / 50

34. Choose from the below what is frequency distribution curves?

35 / 50

35. Pick up the incorrect statement from the below mentioned options?

36 / 50

36. Pick up the correct statement from the following?

37 / 50

37. In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is?

38 / 50

38. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be?

39 / 50

39. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as?

40 / 50

40. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to?

41 / 50

41. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as?

42 / 50

42. The performance of a specific task in CPM, is known as?

43 / 50

43. Bar charts are suitable for which types of works?

44 / 50

44. Choose from the following what does a milestone chart represent as?

45 / 50

45. Mile Stone charts were invented in which year?

46 / 50

46. What is the main principle of an organization?

47 / 50

47. What is the main advantage of line organization?

48 / 50

48. What is the golden rule for the procurement of materials in construction?

49 / 50

49. Construction team includes the following resources?

50 / 50

50. Power stations are generally treated as which type of construtions?