FAQ’s for Project Management Jobs
1 / 50
1. What is the full form of DPR?
2 / 50
2. In india which type of tax system is found?
3 / 50
3. What is the abrevation of TCO?
4 / 50
4. In which form number the first and final bill are maintained?
5 / 50
5. To the contractor we make the payment for work done but the quantity is not measured at the time of payment is called as?
6 / 50
6. In which form no the hand receipt are maintained?
7 / 50
7. All measurements of a work or project are entered in?
8 / 50
8. What is the meaning of intermediate payment?
9 / 50
9. Which of these works are included in Public Works Department?
10 / 50
10. Choose which one are required in a Tender?
11 / 50
11. From the security point of view what is the most suitable time of demolition?
12 / 50
12. Brand value of any construction firm is created because of?
13 / 50
13. The major danger in the constructions are due to?
14 / 50
14. Select the type of measurement book used by the junior engineer from the given options?
15 / 50
15. For recording progress of any construction work is/ are what do we require?
16 / 50
16. The systematic placement of resources in site are termed as?
17 / 50
17. Why do we use Job layout facilitate in construction work to proceed?
18 / 50
18. Which type of organisational structure is mostly followed in civil construction?
19 / 50
19. What is or are the main principle of an organisation?
20 / 50
20. Line organisation is other wise known as?
21 / 50
21. Which of the following does not represent an activity?
22 / 50
22. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?
23 / 50
23. How is an dummy activity is represented?
24 / 50
24. The task performed in CPM is known as?
25 / 50
25. Which one of the following is an activity?
26 / 50
26. In construction project owner may be functional as?
27 / 50
27. What is the main factor which affects the construction of project most?
28 / 50
28. Which of these is the first largest industry in India in term of economic activity?
29 / 50
29. What dose proper Co-ordination of construction means?
30 / 50
30. From the below mentioned optiones which of the following is not role of the contractor
31 / 50
31. In PWD which type of organization is is widely used
32 / 50
32. What is an organization?
33 / 50
33. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.
34 / 50
34. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.
35 / 50
35. from the below given options choose which is an PERT event?
36 / 50
36. What is PERT?
37 / 50
37. The time which results in the least possible construction cost of an activity, is known as?
38 / 50
38. What is a critical ratio scheduling?
39 / 50
39. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?
40 / 50
40. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be?
41 / 50
41. For completion of a project, the critical path of the network represents?
42 / 50
42. The difference between the time available to do a job and the time required to do the job, is known as?
43 / 50
43. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as?
44 / 50
44. An event is indicated on the network by a number enclosed in which symbol?
45 / 50
45. Completion of an activity on CPM network diagram, is generally known as?
46 / 50
46. Critical path method is?
47 / 50
47. What is the main feature of functional organization?
48 / 50
48. A construction schedule is prepared after collecting which of the following data?
49 / 50
49. Before the tender stage what is required?
50 / 50
50. Railway projects are treated as which type of construtions?
Your score is
Restart quiz