/50

FAQ’s for Project Management Jobs

1 / 50

1. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?

2 / 50

2. Which one is an indirect tax?

3 / 50

3. What are the duties of a junior engineer?

4 / 50

4. Public Works Department executes projects primarly of which department?

5 / 50

5. What is the meaning of intermediate payment?

6 / 50

6. To obtain work which sanction is not required?

7 / 50

7. From the security point of view what is the most suitable time of demolition?

8 / 50

8. Brand value of any construction firm is created because of?

9 / 50

9. The major danger in the constructions are due to?

10 / 50

10. What can we stop using Inspection for the site?

11 / 50

11. From the given below options choose in which work, inspection plays a significant role ?

12 / 50

12. What do we call the charts used for the graphical representation of the operation analysis?

13 / 50

13. Select the type of measurement book used by the junior engineer from the given options?

14 / 50

14. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?

15 / 50

15. The analysis of progress of a project is done to achieve?

16 / 50

16. The minimum number of labour required for the applicability of Contract Labour Act?

17 / 50

17. According to minimum wages act normal working hours for adult workers is?

18 / 50

18. A site engineer should ensure to have best output of the work given to the labour must be?

19 / 50

19. What is or are the main principle of an organisation?

20 / 50

20. Line organisation is other wise known as?

21 / 50

21. What are the elements of construction project planning?

22 / 50

22. The task performed in CPM is known as?

23 / 50

23. Which of these is the first largest industry in India in term of economic activity?

24 / 50

24. Railway projects construction comes in which type of construction?

25 / 50

25. Supervision for quality control is the part of which stage

26 / 50

26. Which of the following are the disadvantages of Line and Staff organization?

27 / 50

27. What is an organization?

28 / 50

28. What arethe 4M of construction?

29 / 50

29. A project has three independent critical paths A, B and C. To reduce the project length, which one we have to shorten?

30 / 50

30. Pick up the correct statement regarding CPM from the below mentioned options?

31 / 50

31. If A is the optimistic time, B is the pessimistic time and M is most likely time of an activity, the expected time of the activity, is?

32 / 50

32. What is a critical ratio scheduling?

33 / 50

33. The technique for establishing and maintaining priorities among the various jobs of a project, is known as?

34 / 50

34. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?

35 / 50

35. For completion of a project, the critical path of the network represents?

36 / 50

36. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?

37 / 50

37. What is a dummy activity?

38 / 50

38. The performance of a specific task in CPM, is known as?

39 / 50

39. While scheduling a project by P.M what does he consider?

40 / 50

40. PERT analysis is based on?

41 / 50

41. What was the first method invented for planning projects?

42 / 50

42. Henry Gantt developed Bar charts for planning and scheduling of projects in which year?

43 / 50

43. What is the main feature of functional organization?

44 / 50

44. Frederick W. Taylor introduced a system of working which is known as?

45 / 50

45. The main disadvantage of line organization is?

46 / 50

46. Military organization is known as which type of organization?

47 / 50

47. While filling the tender for any work, the contractor considers which of the following?

48 / 50

48. Time and progress chart of a construction, is also known as?

49 / 50

49. Railway projects are treated as which type of construtions?

50 / 50

50. Works costing less than Rs 20,000 are treated as?

Your score is