FAQ’s for Project Management Jobs
1 / 50
1. Project Repot includes what from the below mentioned options?
2 / 50
2. Which one is an indirect tax?
3 / 50
3. What are the duties of a junior engineer?
4 / 50
4. Rectifications of identified correcttions in cash-book are done using which colur pen?
5 / 50
5. All measurements of a work or project are entered in?
6 / 50
6. For bitumen work what is/are the security measures?
7 / 50
7. to achieve good quality what do we require?
8 / 50
8. Brand value of any construction firm is created because of?
9 / 50
9. The major danger in the constructions are due to?
10 / 50
10. To get a quality work output we need to proper select what?
11 / 50
11. The Triangle of construction management completes with?
12 / 50
12. Select the type of measurement book used by the junior engineer from the given options?
13 / 50
13. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?
14 / 50
14. The analysis of progress of a project is done to achieve?
15 / 50
15. A site engineer should ensure to have best output of the work given to the labour must be?
16 / 50
16. By whome the Job layout is prepared?
17 / 50
17. The systematic placement of resources in site are termed as?
18 / 50
18. The materials stored at the site should be protected from?
19 / 50
19. Name the unit provided for fire hazards safety purposes?
20 / 50
20. Which type of organisational structure is mostly followed in civil construction?
21 / 50
21. Line organisation is other wise known as?
22 / 50
22. Which of the following does not represent an activity?
23 / 50
23. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?
24 / 50
24. What is Slack time?
25 / 50
25. An event is represented in the network through which symbol?
26 / 50
26. Which one of the following is used in PERT method ?
27 / 50
27. What is the oldest method of project planning is?
28 / 50
28. If any activity delayed to their succeeding activity due to some reason, that delay is known as?
29 / 50
29. Which one of the following is an activity?
30 / 50
30. Which one of the following is not a resource of construction industry?
31 / 50
31. A contractor in construction of a project is
32 / 50
32. From the below mentioned optiones which of the following is not arole of the owner
33 / 50
33. Which of the following are the disadvantages of Line and Staff organization?
34 / 50
34. Pick up the correct statement regarding CPM from the below mentioned options?
35 / 50
35. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.
36 / 50
36. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.
37 / 50
37. from the below given options choose which is an PERT event?
38 / 50
38. What is PERT?
39 / 50
39. Critical Path network helps an engineer to understand?
40 / 50
40. Pick up the correct statement from the following?
41 / 50
41. What is a dummy activity?
42 / 50
42. While scheduling a project by P.M what does he consider?
43 / 50
43. Choose from the following what does a milestone chart represent as?
44 / 50
44. The Overall in-charge of an organization at the site responsible for the execution of the works, is called as?
45 / 50
45. What is the main feature of functional organization?
46 / 50
46. Frederick W. Taylor introduced a system of working which is known as?
47 / 50
47. A construction schedule is prepared after collecting which of the following data?
48 / 50
48. Military organization is known as which type of organization?
49 / 50
49. What is the golden rule for the procurement of materials in construction?
50 / 50
50. Construction team includes the following resources?
Your score is
Restart quiz