/50

FAQ’s for Project Management Jobs

1 / 50

1. What is the full form of DPR?

2 / 50

2. In india which type of tax system is found?

3 / 50

3. What is the abrevation of TCO?

4 / 50

4. Rectifications of identified correcttions in cash-book are done using which colur pen?

5 / 50

5. For issue of the stock at store a price per unit is fixed. What is the price called as?

6 / 50

6. In which form no the hand receipt are maintained?

7 / 50

7. All measurements of a work or project are entered in?

8 / 50

8. To obtain work which sanction is not required?

9 / 50

9. What can we improve by the quality control method?

10 / 50

10. The major danger in the constructions are due to?

11 / 50

11. What can we stop using Inspection for the site?

12 / 50

12. From the given below options choose in which work, inspection plays a significant role ?

13 / 50

13. From the given below options choose the functions of the inspection department?

14 / 50

14. What do we call the charts used for the graphical representation of the operation analysis?

15 / 50

15. Which is the famous trade union of India ?

16 / 50

16. What is the aim of organising labour at the site?

17 / 50

17. What is or are the main principle of an organisation?

18 / 50

18. What are the elements of construction project planning?

19 / 50

19. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?

20 / 50

20. Time and progress chart of a construction project is?

21 / 50

21. Finishing of any activity which falls in a CPM network is known as?

22 / 50

22. Which one of the following is not a resource of construction industry?

23 / 50

23. Which of these is the first largest industry in India in term of economic activity?

24 / 50

24. What does the Construction team means?

25 / 50

25. At which stage the contract documents are prepared?

26 / 50

26. Supervision for quality control is the part of which stage

27 / 50

27. From the below mentioned optiones which of the following is not arole of the owner

28 / 50

28. Road is included in which type of constructions mentioned below

29 / 50

29. Consider the following definitions regarding slacks of project activities, from the below mentions options a) The difference between the early start and late start times of a job is called the total slack. b) The critical path is the one whose jobs have zero total slack c) The amount of time by which a job can be delayed without affecting the early start time of any job is called as the free slack d) The difference between the total slack of an activity and the minimum total slack of all its immediate successors is called as free slack.

30 / 50

30. In CPM analysis what do we choose?

31 / 50

31. Pick up the correct statement from the following with regards to P.M. network analysis of projects?

32 / 50

32. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.

33 / 50

33. Choose from the below what is frequency distribution curves?

34 / 50

34. The time which results in the least possible construction cost of an activity, is known as?

35 / 50

35. What is a critical ratio scheduling?

36 / 50

36. Critical Path network helps an engineer to understand?

37 / 50

37. Pick up the correct statement from the following?

38 / 50

38. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?

39 / 50

39. Which one of the following represents an event?

40 / 50

40. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to?

41 / 50

41. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?

42 / 50

42. While scheduling a project by P.M what does he consider?

43 / 50

43. Mile Stone charts were invented in which year?

44 / 50

44. The Overall in-charge of an organization at the site responsible for the execution of the works, is called as?

45 / 50

45. Henry Gantt developed Bar charts for planning and scheduling of projects in which year?

46 / 50

46. The main disadvantage of line organization is?

47 / 50

47. What is the main advantage of line organization?

48 / 50

48. Military organization is known as which type of organization?

49 / 50

49. The final selection of a construction site, is done by?

50 / 50

50. Residential buildings are treated as which type of construtions?

Your score is