FAQ’s for Project Management Jobs
1 / 50
1. In india which type of tax system is found?
2 / 50
2. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?
3 / 50
3. Which one is an indirect tax?
4 / 50
4. Rectifications of identified correcttions in cash-book are done using which colur pen?
5 / 50
5. For allotment of work quotations are invited in which type of system?
6 / 50
6. Which instrument is commonly used for sending an alerts message before starting of danger work?
7 / 50
7. The occurrence of accident in the construction will be effect?
8 / 50
8. What can we improve by the quality control method?
9 / 50
9. To get a quality work output we need to proper select what?
10 / 50
10. The Triangle of construction management completes with?
11 / 50
11. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?
12 / 50
12. The data or the information obtained through the various methods of progress record such as measurement book, job diary, progress report etc, are quantified and analyzed. Name what do we call this process as?
13 / 50
13. What are the following tools are required for the analysis of progress?
14 / 50
14. A site engineer should ensure to have best output of the work given to the labour must be?
15 / 50
15. The systematic placement of resources in site are termed as?
16 / 50
16. Name the unit provided for fire hazards safety purposes?
17 / 50
17. The plan which shows the exact location for placing the resources for construction is known as?
18 / 50
18. Which type of organisation is very popular in Civil Engineering Constructions?
19 / 50
19. What are the elements of construction project planning?
20 / 50
20. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?
21 / 50
21. What does the critical activity shows?
22 / 50
22. If any activity delayed to their succeeding activity due to some reason, that delay is known as?
23 / 50
23. Finishing of any activity which falls in a CPM network is known as?
24 / 50
24. A contractor in construction of a project is
25 / 50
25. What is the main function of the construction management?
26 / 50
26. What are the qualities of good construction manager?
27 / 50
27. From the below mentioned optiones which of the following is not role of the contractor
28 / 50
28. Which of the following is not a characteristics of a Good organization ?
29 / 50
29. A project has three independent critical paths A, B and C. To reduce the project length, which one we have to shorten?
30 / 50
30. Pick up the correct statement regarding CPM from the below mentioned options?
31 / 50
31. In CPM analysis what do we choose?
32 / 50
32. Pick up the correct statement from the following with regards to P.M. network analysis of projects?
33 / 50
33. Critical path lies along the activities having total float?
34 / 50
34. In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is?
35 / 50
35. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?
36 / 50
36. For completion of a project, the critical path of the network represents?
37 / 50
37. The critical activity has?
38 / 50
38. The difference between the time available to do a job and the time required to do the job, is known as?
39 / 50
39. What is a dummy activity?
40 / 50
40. The performance of a specific task in CPM, is known as?
41 / 50
41. Bar charts are suitable for which types of works?
42 / 50
42. The Overall in-charge of an organization at the site responsible for the execution of the works, is called as?
43 / 50
43. What is the main advantage of line organization?
44 / 50
44. Time and progress chart of a construction, is also known as?
45 / 50
45. What is the object of technical planning?
46 / 50
46. Construction team includes the following resources?
47 / 50
47. The final selection of a construction site, is done by?
48 / 50
48. Power stations are generally treated as which type of construtions?
49 / 50
49. Railway projects are treated as which type of construtions?
50 / 50
50. Residential buildings are treated as which type of construtions?
Your score is
Restart quiz