/50

FAQ’s for Project Management Jobs

1 / 50

1. Which one describe the ability to work successfully for a project to meet the futuristic goals?

2 / 50

2. What is the full form of PPP?

3 / 50

3. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?

4 / 50

4. A bussiness started by an enterpreneus with a fresh idea is performing which type of role in busines?

5 / 50

5. Rectifications of identified correcttions in cash-book are done using which colur pen?

6 / 50

6. Tools and plants purchased for general use of division shall be debited to Which Catogery?

7 / 50

7. To the contractor we make the payment for work done but the quantity is not measured at the time of payment is called as?

8 / 50

8. What is the meaning of intermediate payment?

9 / 50

9. The muster roll is maintained in which form no ?

10 / 50

10. Which one is these is an psychological cause of accident?

11 / 50

11. For the success of any construction project what characteristics is/are required?

12 / 50

12. The occurrence of accident in the construction will be effect?

13 / 50

13. The major danger in the constructions are due to?

14 / 50

14. The Triangle of construction management completes with?

15 / 50

15. The site engineer records the quantities of work done at the site and also uses it as a tool for payment to the contractor for his work done in a book. What is the book called as?

16 / 50

16. What is the process called in which the actual field or site progress is compared with the estimated progress?

17 / 50

17. The analysis of progress of a project is done to achieve?

18 / 50

18. Which is the famous trade union of India ?

19 / 50

19. Why do we use Job layout facilitate in construction work to proceed?

20 / 50

20. Who are involved in selection of a construction site?

21 / 50

21. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?

22 / 50

22. What is the oldest method of project planning is?

23 / 50

23. In construction project owner may be functional as?

24 / 50

24. What is the main factor which affects the construction of project most?

25 / 50

25. Which of these is the first largest industry in India in term of economic activity?

26 / 50

26. Construction of the power station comes in which type of construction as per the options mentioned below

27 / 50

27. What are the qualities of good construction manager?

28 / 50

28. Supervision for quality control is the part of which stage

29 / 50

29. What arethe 4M of construction?

30 / 50

30. Pick up the correct statement regarding CPM from the below mentioned options?

31 / 50

31. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.

32 / 50

32. In CPM analysis what do we choose?

33 / 50

33. Pick up the correct statement from the following with regards to P.M. network analysis of projects?

34 / 50

34. If A is the optimistic time, B is the pessimistic time and M is most likely time of an activity, the expected time of the activity, is?

35 / 50

35. What is PERT?

36 / 50

36. In a project logic, four activities M, N, 0 and P are to be completed before starting activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr. respectively, the earliest event occurrence time for the activity Q is?

37 / 50

37. In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is?

38 / 50

38. Which one of the following represents an event?

39 / 50

39. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?

40 / 50

40. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as?

41 / 50

41. While scheduling a project by P.M what does he consider?

42 / 50

42. What was the first method invented for planning projects?

43 / 50

43. Final technical authority of a project lies with whome?

44 / 50

44. The main disadvantage of line organization is?

45 / 50

45. Military organization is known as which type of organization?

46 / 50

46. While filling the tender for any work, the contractor considers which of the following?

47 / 50

47. Modular co-ordination of construction means proper?

48 / 50

48. Construction team includes the following resources?

49 / 50

49. Works costing less than Rs 20,000 are treated as?

50 / 50

50. What should be the minimum cost of a work to be called as project?

Your score is