/50

FAQ’s for Project Management Jobs

1 / 50

1. In which Report do we get the specific activities, events and occurrences?

2 / 50

2. Which one of the below mentioned options is an example of intellectual property?

3 / 50

3. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?

4 / 50

4. If any product is imported by any company from abroad, then which tax is applicable on it?

5 / 50

5. What are the duties of a junior engineer?

6 / 50

6. Rectifications of identified correcttions in cash-book are done using which colur pen?

7 / 50

7. Tools and plants purchased for general use of division shall be debited to Which Catogery?

8 / 50

8. In which form number the measurement Book is maintained?

9 / 50

9. In which form no the hand receipt are maintained?

10 / 50

10. The muster roll is maintained in which form no ?

11 / 50

11. Which of these works are included in Public Works Department?

12 / 50

12. To obtain work which sanction is not required?

13 / 50

13. Choose which one are required in a Tender?

14 / 50

14. For bitumen work what is/are the security measures?

15 / 50

15. What are the cause of the accidents in the project site?

16 / 50

16. The Triangle of construction management completes with?

17 / 50

17. From the given below options choose in which work, inspection plays a significant role ?

18 / 50

18. Select the type of measurement book used by the junior engineer from the given options?

19 / 50

19. Which is the famous trade union of India ?

20 / 50

20. Name the unit provided for fire hazards safety purposes?

21 / 50

21. The plan which shows the exact location for placing the resources for construction is known as?

22 / 50

22. What are the main advantage of line organisation?

23 / 50

23. Who are involved in selection of a construction site?

24 / 50

24. Line organisation is other wise known as?

25 / 50

25. What are the elements of construction project planning?

26 / 50

26. Which one of the following is used in PERT method ?

27 / 50

27. If any activity delayed to their succeeding activity due to some reason, that delay is known as?

28 / 50

28. Finishing of any activity which falls in a CPM network is known as?

29 / 50

29. In construction project owner may be functional as?

30 / 50

30. As per the term economic activity the second largest industry in India is?

31 / 50

31. Construction of the power station comes in which type of construction as per the options mentioned below

32 / 50

32. What are the qualities of good construction manager?

33 / 50

33. What arethe 4M of construction?

34 / 50

34. Pick up the correct statement regarding CPM from the below mentioned options?

35 / 50

35. Consider the following statements regarding slack, choose the correct option; a) The free slack never exceeds the total slack b) The jobs that have total slack need not necessarily have the free slack c) A job can have a free slack only if it has more total slack that the one of its immediate successors.

36 / 50

36. In CPM analysis what do we choose?

37 / 50

37. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.

38 / 50

38. If A is the optimistic time, B is the pessimistic time and M is most likely time of an activity, the expected time of the activity, is?

39 / 50

39. Critical path lies along the activities having total float?

40 / 50

40. Critical Path network helps an engineer to understand?

41 / 50

41. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?

42 / 50

42. The estimated time required to perform an activity, is known as?

43 / 50

43. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?

44 / 50

44. PERT analysis is based on?

45 / 50

45. Choose from the following what does a milestone chart represent as?

46 / 50

46. Henry Gantt developed Bar charts for planning and scheduling of projects in which year?

47 / 50

47. What is the main advantage of line organization?

48 / 50

48. While filling the tender for any work, the contractor considers which of the following?

49 / 50

49. Time and progress chart of a construction, is also known as?

50 / 50

50. Modular co-ordination of construction means proper?

Your score is