FAQ’s for Project Management Jobs
1 / 50
1. Which one of the below mentioned options is an example of intellectual property?
2 / 50
2. What is the full form of PPP?
3 / 50
3. What is the full form of DPR?
4 / 50
4. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?
5 / 50
5. Public Works Department executes projects primarly of which department?
6 / 50
6. To the contractor we make the payment for work done but the quantity is not measured at the time of payment is called as?
7 / 50
7. All measurements of a work or project are entered in?
8 / 50
8. Which of these works are included in Public Works Department?
9 / 50
9. For bitumen work what is/are the security measures?
10 / 50
10. At which stage of construction, the inspection is required for error-free work to be executed?
11 / 50
11. What do we call the charts used for the graphical representation of the operation analysis?
12 / 50
12. For recording progress of any construction work is/ are what do we require?
13 / 50
13. The materials stored at the site should be protected from?
14 / 50
14. The major principle of storing and stacking of any materials is to achieve with?
15 / 50
15. Which type of organisational structure is mostly followed in civil construction?
16 / 50
16. What are the factors on which the job layout for any project will depend?
17 / 50
17. What are the main advantage of line organisation?
18 / 50
18. What is the first stage of a construction?
19 / 50
19. What is or are the main principle of an organisation?
20 / 50
20. What is Slack time?
21 / 50
21. Which one of the following is used in PERT method ?
22 / 50
22. Time and progress chart of a construction project is?
23 / 50
23. Which one of the following is an activity?
24 / 50
24. Which one of the following is not a resource of construction industry?
25 / 50
25. Which of these is the first largest industry in India in term of economic activity?
26 / 50
26. Railway projects construction comes in which type of construction?
27 / 50
27. What is the main function of the construction management?
28 / 50
28. From the below mentioned optiones which of the following is not role of the contractor
29 / 50
29. In PWD which type of organization is is widely used
30 / 50
30. Which of the following is not a characteristics of a Good organization ?
31 / 50
31. Road is included in which type of constructions mentioned below
32 / 50
32. Pick up the correct statement regarding CPM from the below mentioned options?
33 / 50
33. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.
34 / 50
34. In CPM analysis what do we choose?
35 / 50
35. Choose from the below what is frequency distribution curves?
36 / 50
36. What is CPM?
37 / 50
37. Critical path lies along the activities having total float?
38 / 50
38. Critical Path network helps an engineer to understand?
39 / 50
39. In a project logic, four activities M, N, 0 and P are to be completed before starting activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr. respectively, the earliest event occurrence time for the activity Q is?
40 / 50
40. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to?
41 / 50
41. While scheduling a project by P.M what does he consider?
42 / 50
42. Bar charts are suitable for which types of works?
43 / 50
43. Choose from the following what does a milestone chart represent as?
44 / 50
44. Various activities of a project, are shown on bar charts in which format?
45 / 50
45. Site order book is used for recording what?
46 / 50
46. What is the main principle of an organization?
47 / 50
47. What is the golden rule for the procurement of materials in construction?
48 / 50
48. Construction team includes the following resources?
49 / 50
49. The final selection of a construction site, is done by?
50 / 50
50. Works costing less than Rs 20,000 are treated as?
Your score is
Restart quiz