FAQ’s for Project Management Jobs
1 / 50
1. In which Report do we get the specific activities, events and occurrences?
2 / 50
2. Which one of the below mentioned options is an example of intellectual property?
3 / 50
3. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?
4 / 50
4. If any product is imported by any company from abroad, then which tax is applicable on it?
5 / 50
5. What are the duties of a junior engineer?
6 / 50
6. Rectifications of identified correcttions in cash-book are done using which colur pen?
7 / 50
7. Tools and plants purchased for general use of division shall be debited to Which Catogery?
8 / 50
8. In which form number the measurement Book is maintained?
9 / 50
9. In which form no the hand receipt are maintained?
10 / 50
10. The muster roll is maintained in which form no ?
11 / 50
11. Which of these works are included in Public Works Department?
12 / 50
12. To obtain work which sanction is not required?
13 / 50
13. Choose which one are required in a Tender?
14 / 50
14. For bitumen work what is/are the security measures?
15 / 50
15. What are the cause of the accidents in the project site?
16 / 50
16. The Triangle of construction management completes with?
17 / 50
17. From the given below options choose in which work, inspection plays a significant role ?
18 / 50
18. Select the type of measurement book used by the junior engineer from the given options?
19 / 50
19. Which is the famous trade union of India ?
20 / 50
20. Name the unit provided for fire hazards safety purposes?
21 / 50
21. The plan which shows the exact location for placing the resources for construction is known as?
22 / 50
22. What are the main advantage of line organisation?
23 / 50
23. Who are involved in selection of a construction site?
24 / 50
24. Line organisation is other wise known as?
25 / 50
25. What are the elements of construction project planning?
26 / 50
26. Which one of the following is used in PERT method ?
27 / 50
27. If any activity delayed to their succeeding activity due to some reason, that delay is known as?
28 / 50
28. Finishing of any activity which falls in a CPM network is known as?
29 / 50
29. In construction project owner may be functional as?
30 / 50
30. As per the term economic activity the second largest industry in India is?
31 / 50
31. Construction of the power station comes in which type of construction as per the options mentioned below
32 / 50
32. What are the qualities of good construction manager?
33 / 50
33. What arethe 4M of construction?
34 / 50
34. Pick up the correct statement regarding CPM from the below mentioned options?
35 / 50
35. Consider the following statements regarding slack, choose the correct option; a) The free slack never exceeds the total slack b) The jobs that have total slack need not necessarily have the free slack c) A job can have a free slack only if it has more total slack that the one of its immediate successors.
36 / 50
36. In CPM analysis what do we choose?
37 / 50
37. Consider the following statements regarding the critical path of a project network. choose the correct option a) path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal. b) The length of a path in a network is the total time it takes to travel the path. c) The shortest path in a project network is called critical path, d)Activities on the critical path are called critical activities.
38 / 50
38. If A is the optimistic time, B is the pessimistic time and M is most likely time of an activity, the expected time of the activity, is?
39 / 50
39. Critical path lies along the activities having total float?
40 / 50
40. Critical Path network helps an engineer to understand?
41 / 50
41. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?
42 / 50
42. The estimated time required to perform an activity, is known as?
43 / 50
43. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?
44 / 50
44. PERT analysis is based on?
45 / 50
45. Choose from the following what does a milestone chart represent as?
46 / 50
46. Henry Gantt developed Bar charts for planning and scheduling of projects in which year?
47 / 50
47. What is the main advantage of line organization?
48 / 50
48. While filling the tender for any work, the contractor considers which of the following?
49 / 50
49. Time and progress chart of a construction, is also known as?
50 / 50
50. Modular co-ordination of construction means proper?
Your score is
Restart quiz