FAQ’s for Project Management Jobs
1 / 50
1. In which Report do we get the specific activities, events and occurrences?
2 / 50
2. Project Repot includes what from the below mentioned options?
3 / 50
3. What is the full form of PPP?
4 / 50
4. What is the full form of DPR?
5 / 50
5. What is the abrevation of TCO?
6 / 50
6. Public Works Department executes projects primarly of which department?
7 / 50
7. In which form number the measurement Book is maintained?
8 / 50
8. In which form number the first and final bill are maintained?
9 / 50
9. The muster roll is maintained in which form no ?
10 / 50
10. Which one is these is an psychological cause of accident?
11 / 50
11. Which instrument is commonly used for sending an alerts message before starting of danger work?
12 / 50
12. to achieve good quality what do we require?
13 / 50
13. At which stage of construction, the inspection is required for error-free work to be executed?
14 / 50
14. The minimum number of labour required for the applicability of Contract Labour Act?
15 / 50
15. According to minimum wages act normal working hours for adult workers is?
16 / 50
16. What are the main advantage of line organisation?
17 / 50
17. What is the first stage of a construction?
18 / 50
18. What is or are the main principle of an organisation?
19 / 50
19. Which type of organisation is very popular in Civil Engineering Constructions?
20 / 50
20. From the below given options choose time estimates of activities and probability of their occurrence followed by PERT analysis is called as?
21 / 50
21. Time and progress chart of a construction project is?
22 / 50
22. What is the main factor which affects the construction of project most?
23 / 50
23. Construction of the power station comes in which type of construction as per the options mentioned below
24 / 50
24. As pet the below mentioned optioned each work should be planned with respect to?
25 / 50
25. What is the main function of the construction management?
26 / 50
26. What arethe 4M of construction?
27 / 50
27. Consider the following definitions regarding slacks of project activities, from the below mentions options a) The difference between the early start and late start times of a job is called the total slack. b) The critical path is the one whose jobs have zero total slack c) The amount of time by which a job can be delayed without affecting the early start time of any job is called as the free slack d) The difference between the total slack of an activity and the minimum total slack of all its immediate successors is called as free slack.
28 / 50
28. Consider the following statements regarding Early start and early finish times, Choose the corrcet option. a) The earliest possible that the job can begin, is called the early start of the job b) The early finish of a job is early start time plus the job’s completion time c) For jobs with no predecessors, the early start is equal to start time of the project d) The early start of a job is the largest of the early finish times of all of the immediately predecessors.
29 / 50
29. In CPM analysis what do we choose?
30 / 50
30. A CPM family includes which of the following?
31 / 50
31. The time which results in the least possible construction cost of an activity, is known as?
32 / 50
32. Critical path lies along the activities having total float?
33 / 50
33. Critical Path network helps an engineer to understand?
34 / 50
34. In a project logic, four activities M, N, 0 and P are to be completed before starting activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr. respectively, the earliest event occurrence time for the activity Q is?
35 / 50
35. Which one of the following represents an event?
36 / 50
36. Critical path method is?
37 / 50
37. Bar charts are suitable for which types of works?
38 / 50
38. What was the first method invented for planning projects?
39 / 50
39. For the supply of materials for concrete, farm work reinforcing and placing of concrete, removal of farm work and curing of concrete, number of bar(s) required on bar chart, is?
40 / 50
40. The Overall in-charge of an organization at the site responsible for the execution of the works, is called as?
41 / 50
41. Henry Gantt developed Bar charts for planning and scheduling of projects in which year?
42 / 50
42. What is the main principle of an organization?
43 / 50
43. What is the most popular type of organization used for Civil Engineering Constructions?
44 / 50
44. Military organization is known as which type of organization?
45 / 50
45. While filling the tender for any work, the contractor considers which of the following?
46 / 50
46. Time and progress chart of a construction, is also known as?
47 / 50
47. Before the tender stage what is required?
48 / 50
48. Railway projects are treated as which type of construtions?
49 / 50
49. Residential buildings are treated as which type of construtions?
50 / 50
50. Works costing less than Rs 20,000 are treated as?
Your score is
Restart quiz