/50

FAQ’s for Project Management Jobs

1 / 50

1. In which Report do we get the specific activities, events and occurrences?

2 / 50

2. Which one of the below mentioned options is an example of intellectual property?

3 / 50

3. Which tax is imposed by the Central Government but the state government collects the tax. What is that tax called as?

4 / 50

4. Which one is an indirect tax?

5 / 50

5. What is the abrevation of TCO?

6 / 50

6. A bussiness started by an enterpreneus with a fresh idea is performing which type of role in busines?

7 / 50

7. What are the duties of a junior engineer?

8 / 50

8. For issue of the stock at store a price per unit is fixed. What is the price called as?

9 / 50

9. Tools and plants purchased for general use of division shall be debited to Which Catogery?

10 / 50

10. In which form number the first and final bill are maintained?

11 / 50

11. To the contractor we make the payment for work done but the quantity is not measured at the time of payment is called as?

12 / 50

12. In which form no the hand receipt are maintained?

13 / 50

13. What is the meaning of intermediate payment?

14 / 50

14. Which of these works are included in Public Works Department?

15 / 50

15. To obtain work which sanction is not required?

16 / 50

16. The occurrence of accident in the construction will be effect?

17 / 50

17. to achieve good quality what do we require?

18 / 50

18. What can we stop using Inspection for the site?

19 / 50

19. From the given below options choose the functions of the inspection department?

20 / 50

20. The data or the information obtained through the various methods of progress record such as measurement book, job diary, progress report etc, are quantified and analyzed. Name what do we call this process as?

21 / 50

21. The analysis of progress of a project is done to achieve?

22 / 50

22. Which is the famous trade union of India ?

23 / 50

23. By whome the Job layout is prepared?

24 / 50

24. The major principle of storing and stacking of any materials is to achieve with?

25 / 50

25. What is or are the main principle of an organisation?

26 / 50

26. Line organisation is other wise known as?

27 / 50

27. Which of the following is an event ?

28 / 50

28. Which one of the following is used in PERT method ?

29 / 50

29. Time and progress chart of a construction project is?

30 / 50

30. If any activity delayed to their succeeding activity due to some reason, that delay is known as?

31 / 50

31. The task performed in CPM is known as?

32 / 50

32. At which stage the tests for performance of construction is done

33 / 50

33. Pick up the correct statement regarding PERT from the below mwntioned options?

34 / 50

34. In CPM analysis what do we choose?

35 / 50

35. Pick up the correct statement from the following with regards to P.M. network analysis of projects?

36 / 50

36. What is CPM?

37 / 50

37. The technique for establishing and maintaining priorities among the various jobs of a project, is known as?

38 / 50

38. In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is?

39 / 50

39. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following?

40 / 50

40. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then which of the following relation holds good?

41 / 50

41. Critical path method is?

42 / 50

42. Choose from the following what does a milestone chart represent as?

43 / 50

43. Various activities of a project, are shown on bar charts in which format?

44 / 50

44. The Overall in-charge of an organization at the site responsible for the execution of the works, is called as?

45 / 50

45. What is the main principle of an organization?

46 / 50

46. What is the most popular type of organization used for Civil Engineering Constructions?

47 / 50

47. A construction schedule is prepared after collecting which of the following data?

48 / 50

48. Time and progress chart of a construction, is also known as?

49 / 50

49. What is the object of technical planning?

50 / 50

50. Before the tender stage what is required?

Your score is