/50
1

FAQ’s for Quantity surveyor Jobs

1 / 50

1. What is the meaning of Cost?

2 / 50

2. What is the meaning of Price?

3 / 50

3. What do we call a person who takes the lease of any thing?

4 / 50

4. The Owner who allows another person to enjoy rights over his property is called as?

5 / 50

5. When we pay annuity at the end of each period for a certain number of years, what is it called as?

6 / 50

6. What do we call when the capital sum required to be invested in order to receive an annuity at certain rate of interest, is called as?

7 / 50

7. The net instalment of annual or periodical payment for repayment of capital amount invested in a property for a specified period is called as?

8 / 50

8. The value of a property at the end of its usefull life with out dismanteling it is called as?

9 / 50

9. Calcualte the quantity of sand required for 10 m³ of 1:2:4 cement concrete?

10 / 50

10. Calculate the quantity of cement required for 10 m³ of 1: 2 : 4 cement concrete?

11 / 50

11. 1 bag of cement of 50 kgs covers how much volume?

12 / 50

12. Calculate the quantity of sand required for 5 m³ of brick work in cement mortar 1: 6?

13 / 50

13. Calculate the quantity of cement required for 10 m³ of brick work in cement mortar 1: 3?

14 / 50

14. Which IS Code do we use for mode of measurment?

15 / 50

15. What is the cost of a building which consist of 400 cubic meters. The rate per cubic meter is Rs. 180/- ?

16 / 50

16. What do we call the process of calculating the quantities of various items required for complete the project?

17 / 50

17. What is the process of calculating the quantities and costs of the various items required to complete the work is called as?

18 / 50

18. What si the standard size of a normal brick?

19 / 50

19. Different weather conditions like extreme cold, heat or rain how will they effect the project?

20 / 50

20. What is the name given to the rate per unit of a particular item of work, from the cost of quantities of materials, the cost of labors, the cost of equipments and other miscellaneous petty expenses require for the completion of the project?

21 / 50

21. Is the below statement True of False, Bricks shall be laid in English bond unless otherwise specified?

22 / 50

22. As per which IS Code the cement should be used in the specifications?

23 / 50

23. What is the unit of measurment of excavation?

24 / 50

24. In the contract document which type of specificaitons is a part of it?

25 / 50

25. Specifications are divided in to two catogories the first one is general specifications or brief specificatons and what is the second one called as?

26 / 50

26. Choose form the below mentioned options what is or are the Important contract documents?

27 / 50

27. What is the unit of measurment of Centering and shuttering?

28 / 50

28. The brick massonary for honey comb massonary is measured in?

29 / 50

29. Generally the Skirting is measured in?

30 / 50

30. For hard soil the earthwork excavation is measured in?

31 / 50

31. The steel used in the reinforcments is mearuded in?

32 / 50

32. What is the Unit of measurment of Cement?

33 / 50

33. While doing backfilling or refilling earthwork in foundation pit the thickness should not exceed for each layer?

34 / 50

34. From the below mentioned options select which one is not a spot item?

35 / 50

35. The amount which is provided in the estimate and bill of quantities for some specialized work to be done by a specialized firm; whose details are not known at the time of preparing estimate is called as?

36 / 50

36. What is the order or sequence of measurment as per ISI method which is to be used?

37 / 50

37. From the below mentioned options choose what is required while preparing a detailed estimate?

38 / 50

38. What is the unit of stadium used for the usage?

39 / 50

39. What is the unit of dam used to measure for usage?

40 / 50

40. When we modifying the original detailed estimate and prepare a new estimate what is it called as?

41 / 50

41. To prepare an proper estimate of a work we requier Drawing, Specifications and what?

42 / 50

42. After knowing the quantittes of various items and their unit rate we calculate the Propable cost of the project what is it called as?

43 / 50

43. What is the process of calculating the quantities of various items for any construction work is is called as?

44 / 50

44. How much % of balcony area is included in the floor area?

45 / 50

45. If there are changes in the price we prepare a revise estimate is the sanction estimate exceeds how much % ?

46 / 50

46. For the construction of buildings, What are the subheads of the estimate for construction of building?

47 / 50

47. The omitted cover of concrete is assumed to be for estimating a reinforced cement structure?

48 / 50

48. Which of these does not include the plinth area of a building?

49 / 50

49. How much water is required for one kg distemper?

50 / 50

50. For one Cubic Meter of brick masonary how many bricks are required?

Your score is