FAQ’s for Quantity surveyor Jobs
1 / 50
1. The charges represented directly in the commodity produced are called as?
2 / 50
2. What is the meaning of Price?
3 / 50
3. The perpetuity lease(Endless Duration) is granted for how many years?
4 / 50
4. What do we call when the capital sum required to be invested in order to receive an annuity at certain rate of interest, is called as?
5 / 50
5. From the total cost of the construction how much % is the scrap value of the building?
6 / 50
6. If we sell a property lower than the market value of that time is said to have what value?
7 / 50
7. When we dismantel the property when we can not use the property for usage we try to sell that waste materila, what do we call that value as?
8 / 50
8. As per the standards what is the length of a steel rod in meters?
9 / 50
9. Calcualte the quantity of sand required for 10 m³ of 1:2:4 cement concrete?
10 / 50
10. Calculate the quantity of cement required for 10 m³ of 1: 2 : 4 cement concrete?
11 / 50
11. Which IS Code do we use for mode of measurment?
12 / 50
12. What is the cost of a building which consist of 400 cubic meters. The rate per cubic meter is Rs. 180/- ?
13 / 50
13. What do we call the process of determining the probable cost of the project after knowing the quantities of various items and their unit rate is called as?
14 / 50
14. What do we call the process of calculating the quantities of various items required for complete the project?
15 / 50
15. What is the process of calculating the quantities and costs of the various items required to complete the work is called as?
16 / 50
16. What si the standard size of a normal brick?
17 / 50
17. Different weather conditions like extreme cold, heat or rain how will they effect the project?
18 / 50
18. As per IS: 269, what should be the minimum compressive strength of Ordinary Portland Cement?
19 / 50
19. While we make specifications the sentence shall be in which format?
20 / 50
20. In the contract document which type of specificaitons is a part of it?
21 / 50
21. In the contract document which type of specificaitons is not a part of it?
22 / 50
22. What is the term given for the detailed description of the quality of materials and workmanship required to complete an engineering project in accordance with its drawings and details?
23 / 50
23. What is the unit of measurment of Centering and shuttering?
24 / 50
24. What is the unit of measurment of damp proof course (D.P.C.)?
25 / 50
25. The birck work done in Foundation, Plinth level, Supestructure are measured in?
26 / 50
26. what is the unit of measurment of Surface dressing?
27 / 50
27. The steel used in the reinforcments is mearuded in?
28 / 50
28. In measuring plastering, no deduction is made for opening up to/ While we are doing the calcualtions for the palstering we don’t do the deductions for opening up to how many m²?
29 / 50
29. While doing backfilling or refilling earthwork in foundation pit the thickness should not exceed for each layer?
30 / 50
30. The bricks for masonry structure are measured in cubic meters except in the case of?
31 / 50
31. When we are measuring the weight of an item we corrrectly measure nearest to how much Kgs?
32 / 50
32. Choose from the below given options what do we consider while preparing a detailed estimate?
33 / 50
33. When we are measuring an area we measure it correctly and nearest to?
34 / 50
34. From the below mentioned options choose what is required while preparing a detailed estimate?
35 / 50
35. How much % of amount from detail estimate is their for work charged establishment?
36 / 50
36. The provision of an incidental expense variation in detailed estimate is how much % ?
37 / 50
37. What is the term give to the procedure of costing or valuing an item of work on the basis of actual laborers and materials required?
38 / 50
38. What is the abbreviation of CBRI?
39 / 50
39. The Electrification cost of a building is how much % of total estimate?
40 / 50
40. What is the meaning of Floor area?
41 / 50
41. While preparing the plint area estimate from the below mentioned options which item is not included?
42 / 50
42. What is the unit of stadium used for the usage?
43 / 50
43. What is the unit of dam used to measure for usage?
44 / 50
44. We use appoximate estimate to prepare an estimate for an work what is also known as?
45 / 50
45. After knowing the quantittes of various items and their unit rate we calculate the Propable cost of the project what is it called as?
46 / 50
46. From the below mentioned options choose which is not included in the carpet area?
47 / 50
47. If there are changes in the price we prepare a revise estimate is the sanction estimate exceeds how much % ?
48 / 50
48. What is the actual size of a modular brick according to Indian Standard institute?
49 / 50
49. The omitted cover of concrete is assumed to be for estimating a reinforced cement structure?
50 / 50
50. To do a work the rate of an item depends on?
Your score is
Restart quiz