/50
1

FAQ’s for Quantity surveyor Jobs

1 / 50

1. What is the meaning of Cost?

2 / 50

2. What do we call a person who takes the lease of any thing?

3 / 50

3. The perpetuity lease(Endless Duration) is granted for how many years?

4 / 50

4. When we remove the original value from the depeciation value what do we get?

5 / 50

5. When we dismantel the property when we can not use the property for usage we try to sell that waste materila, what do we call that value as?

6 / 50

6. As per the standards what is the length of a steel rod in meters?

7 / 50

7. Calculate the quantity of aggregate required for 10 m³ of 1:2:4 cement concrete?

8 / 50

8. 1 bag of cement of 50 kgs covers how much volume?

9 / 50

9. Calculate the quantity of sand required for 5 m³ of brick work in cement mortar 1: 6?

10 / 50

10. Calculate the quantity of cement required for 10 m³ of brick work in cement mortar 1: 3?

11 / 50

11. What si the standard size of a normal brick?

12 / 50

12. What do we call the work done per day by a skilled labour to complete the quantity of work?

13 / 50

13. For the list of rates of various items is prepared after the analysis of rates and document is prepared. What is that document called as?

14 / 50

14. What is the name given to the rate per unit of a particular item of work, from the cost of quantities of materials, the cost of labors, the cost of equipments and other miscellaneous petty expenses require for the completion of the project?

15 / 50

15. As per which IS Code the cement should be used in the specifications?

16 / 50

16. What is the unit of measurment of excavation?

17 / 50

17. In the contract document which type of specificaitons is a part of it?

18 / 50

18. In the contract document which type of specificaitons is not a part of it?

19 / 50

19. Specifications are divided in to two catogories the first one is general specifications or brief specificatons and what is the second one called as?

20 / 50

20. Choose form the below mentioned options what is or are the Important contract documents?

21 / 50

21. The unit of measurement of steel railing is?

22 / 50

22. The brick massonary for honey comb massonary is measured in?

23 / 50

23. Generally the Skirting is measured in?

24 / 50

24. When we measure the wood, what units do use to measure them?

25 / 50

25. In measuring plastering, no deduction is made for opening up to/ While we are doing the calcualtions for the palstering we don’t do the deductions for opening up to how many m²?

26 / 50

26. While doing backfilling or refilling earthwork in foundation pit the thickness should not exceed for each layer?

27 / 50

27. The bricks for masonry structure are measured in cubic meters except in the case of?

28 / 50

28. When we are measuring the weight of an item we corrrectly measure nearest to how much Kgs?

29 / 50

29. When we are measuring an area we measure it correctly and nearest to?

30 / 50

30. Which IS Code do we use for mode of measurment?

31 / 50

31. The provision of an incidental expense variation in detailed estimate is how much % ?

32 / 50

32. For some items it is hard for the for the estimator to fix an amount without seeing and studying them in detail. Such items are known as?

33 / 50

33. What is the term give to the procedure of costing or valuing an item of work on the basis of actual laborers and materials required?

34 / 50

34. The area of our house in which we can live is called as?

35 / 50

35. What is the meaning of Floor area?

36 / 50

36. Based on the plinth area of the building which estimate is prepared?

37 / 50

37. What is the unit of stadium used for the usage?

38 / 50

38. What is the unit of dam used to measure for usage?

39 / 50

39. When we modifying the original detailed estimate and prepare a new estimate what is it called as?

40 / 50

40. We use appoximate estimate to prepare an estimate for an work what is also known as?

41 / 50

41. What is the process of calculating the quantities of various items for any construction work is is called as?

42 / 50

42. The calculation of the quantities and costs of the various items required for work is called as?

43 / 50

43. Pick up the correct statement from the below mentioned options?

44 / 50

44. Which one of the following is the most reliable estimate?

45 / 50

45. If there are changes in the price we prepare a revise estimate is the sanction estimate exceeds how much % ?

46 / 50

46. For which item the measurement is not made in square meters?

47 / 50

47. For the construction of buildings, What are the subheads of the estimate for construction of building?

48 / 50

48. What is the actual size of a modular brick according to Indian Standard institute?

49 / 50

49. Which of these does not include the plinth area of a building?

50 / 50

50. For one Cubic Meter of brick masonary how many bricks are required?

Your score is