FAQ’s for Quantity surveyor Jobs
1 / 50
1. The charges represented directly in the commodity produced are called as?
2 / 50
2. When we deduct outging amount from the gross income what do we call it as?
3 / 50
3. When we pay annuity at the end of each period for a certain number of years, what is it called as?
4 / 50
4. what do we call when we try to recive annuity for an indefinite period?
5 / 50
5. What do we call when the capital sum required to be invested in order to receive an annuity at certain rate of interest, is called as?
6 / 50
6. If a property is capable of fetching more return due to its alternative use or by providing some development works, such inherent value of a property is known as?
7 / 50
7. The value of a property at the end of its usefull life with out dismanteling it is called as?
8 / 50
8. Calcualte the quantity of sand required for 10 m³ of 1:2:4 cement concrete?
9 / 50
9. Calculate the quantity of aggregate required for 10 m³ of 1:2:4 cement concrete?
10 / 50
10. Calculate the quantity of cement required for 10 m³ of 1: 2 : 4 cement concrete?
11 / 50
11. Calculate the quantity of sand required for 5 m³ of brick work in cement mortar 1: 6?
12 / 50
12. How many bricks are required for 15 Cu.m of brick masonry work?
13 / 50
13. Which IS Code do we use for mode of measurment?
14 / 50
14. What do we call the process of determining the probable cost of the project after knowing the quantities of various items and their unit rate is called as?
15 / 50
15. What is the process of calculating the quantities and costs of the various items required to complete the work is called as?
16 / 50
16. What si the standard size of a normal brick?
17 / 50
17. For the list of rates of various items is prepared after the analysis of rates and document is prepared. What is that document called as?
18 / 50
18. For any work the rate of an item depends on which one of the following mentioned below?
19 / 50
19. As per IS: 269, what should be the minimum compressive strength of Ordinary Portland Cement?
20 / 50
20. As per which IS Code the cement should be used in the specifications?
21 / 50
21. What is the unit of measurment of excavation?
22 / 50
22. In all engineering departments they prepare detailed specifications of certain common items of construction and publish them in book form. What are such types of specifications called as?
23 / 50
23. Choose form the below mentioned options what is or are the Important contract documents?
24 / 50
24. What is the term given for the detailed description of the quality of materials and workmanship required to complete an engineering project in accordance with its drawings and details?
25 / 50
25. What is the unit of measurment of Centering and shuttering?
26 / 50
26. The unit of measurement of steel railing is?
27 / 50
27. When we measure the wood, what units do use to measure them?
28 / 50
28. In measuring plastering, no deduction is made for opening up to/ While we are doing the calcualtions for the palstering we don’t do the deductions for opening up to how many m²?
29 / 50
29. While doing backfilling or refilling earthwork in foundation pit the thickness should not exceed for each layer?
30 / 50
30. The amount which is provided in the estimate and bill of quantities for some specialized work to be done by a specialized firm; whose details are not known at the time of preparing estimate is called as?
31 / 50
31. From the below mentioned options choose what is required while preparing a detailed estimate?
32 / 50
32. For some items it is hard for the for the estimator to fix an amount without seeing and studying them in detail. Such items are known as?
33 / 50
33. What is the term give to the procedure of costing or valuing an item of work on the basis of actual laborers and materials required?
34 / 50
34. What is the abbreviation of CBRI?
35 / 50
35. What is the meaning of Floor area?
36 / 50
36. While preparing the plint area estimate from the below mentioned options which item is not included?
37 / 50
37. Based on the plinth area of the building which estimate is prepared?
38 / 50
38. What is the unit of hospitals used for repesenting the usage of hospital?
39 / 50
39. When we modifying the original detailed estimate and prepare a new estimate what is it called as?
40 / 50
40. From the below mentioned options choose which estimate is least accurate to work?
41 / 50
41. To prepare an proper estimate of a work we requier Drawing, Specifications and what?
42 / 50
42. What is the process of calculating the quantities of various items for any construction work is is called as?
43 / 50
43. How much % of balcony area is included in the floor area?
44 / 50
44. Pick up the correct statement from the below mentioned options?
45 / 50
45. Which one of the following is the most reliable estimate?
46 / 50
46. If there are changes in the price we prepare a revise estimate is the sanction estimate exceeds how much % ?
47 / 50
47. For which item the measurement is not made in square meters?
48 / 50
48. For the construction of buildings, What are the subheads of the estimate for construction of building?
49 / 50
49. Which of these does not include the plinth area of a building?
50 / 50
50. To do a work the rate of an item depends on?
Your score is
Restart quiz